Friday, June 27, 2008

June 27, 2008

The roof is almost completely finished on the main building. By the end of the day the roof of the main building should be finished and the roof should start going up on the educational wing. If all goes well, by Tuesday the roof should be shingled.

June 26, 2008

All the walls are built and the roof is going up.

Monday, June 23, 2008

June 23, 2008

The walls are going up! If all goes well, by Friday the building should be under roof.

Wednesday, June 18, 2008

June 18, 2008

With the plumbing inspection passed, it's time to pour in the concrete!

June 13, 2008

Plumbing is going in and ready to be inspected.


May 31, 2008

The concrete walls are poured. Ready for plumbing to go in.